June 19, 2026--Construction progresses on our new high school site with many new projects occurring this week. First, a new concrete pour occurred this morning in the auditorium location. Initially, the first pour was made on the lower level and the remainder of the foundation was completed this morning.
Second, steel beams continue to go up and a roof is over the new gym area at this time. You can see where the gym entrance will be in relation to the classroom spaces just to the east of the gym.
Finally, work continues at the baseball/softball fields with the steel frame going up for the concession stand and restroom space. Foundation and plumbing has been completed for this area so work will continue on the exterior and interior spaces. #TPND